Marsden Primary School's pitched roof is recovered by John Flowers
- South Tyneside Council
- North East
- Call-off
- 27 July 2026 to 27 September 2026
South Tyneside Council hired John Flowers Limited to replace the pitched roof over parts of Marsden Primary School in Whitburn.
The contractor was to strip out the old roofing and lay clay tiles over new timber, insulation and a breather membrane.
The council placed the order through Lot 1 of its own framework for pitched and flat roof coverings. The £185,519 contract ran from July 2026 and was due to end in September 2026.
- What
- Pitched roofing
- Supplier
- John Flowers Limited
- Value
- £185,519
- How it was bought
- Call-off, South Tyneside Council
- Dates and next
- Jul 2026 to Sep 2026