Exeter Main Operating Base: ambulance trust wants it designed and built
- South Western Ambulance Service NHS Foundation Trust
- South West
- Competitive flexible procedure
- 6 May 2027 to 31 March 2029
South Western Ambulance Service NHS Foundation Trust wants a contractor to design and build a new Main Operating Base in Exeter. Firms first fill in a supplier questionnaire, and those shortlisted go on to the full tender.
Cost counts for 60% of the score, quality and technical questions for 30% and social value for 10%. The trust's earlier plans put the estimate at £25m and then £15m.
The work is estimated at £11.65m. The deadline for bids is 7 December 2026, and the build is due to start in May 2027.
Closes in 15 days· 7 Dec 2026
- What
- New-build construction of non-residential buildings
- Estimated value
- £11.7m
- How it is being bought
- Competitive flexible procedure
- Bids due
- 7 Dec 2026
- Contract dates
- May 2027 to Mar 2029
- Option to Apr 2029