Schofield Groundworks refurbishes Southampton's Shirley Ponds Skatepark
- Southampton City Council
- South East
- Below threshold - without competition
- 6 August 2026 to 5 August 2027
Southampton City Council hired Schofield Groundworks Limited to refurbish Shirley Ponds Skatepark in reinforced concrete.
The existing ramps and trick features stay in place and serve as permanent formwork. New concrete encases them, so the old equipment does not have to be demolished and removed. The council says this cuts both cost and environmental impact. Beneath the new slabs and riding surfaces go a Type 1 sub-base, imported fill and a geotextile membrane, once the site has been dug out and levelled.
The council awarded the £255,000 contract directly, without a competition, in August 2026. It runs to August 2027.
Contract ends August 2027
- What
- Skate parks, pump tracks and wheeled sports facilities
- Supplier
- Schofield Groundworks Limited
- Value
- £255,000
- How it was bought
- Below threshold - without competition
- Dates and next