DM Habens repairs St Denys School soffits and fascias for Southampton
- Southampton City Council
- South East
- Below threshold - limited competition, 5 bids
- 1 July 2026 to 31 August 2026
Southampton City Council hired DM Habens (The Builder) Ltd for repair and replacement work on the soffit and fascia of St Denys School. It was a two-month job on the outside of the school building.
The council ran a limited competition and received five bids. DM Habens, a small business, won the £57,178 contract in June 2026, and the work was due to finish in August 2026.
- What
- Rainwater goods, fascias, soffits and gutter maintenance
- Supplier
- DM Habens (The Builder) Ltd
- Value
- £57,178
- How it was bought
- Below threshold - limited competition
- 5 bids
- Dates and next
- Jul 2026 to Aug 2026