West End Road flood scheme for St Helens goes to George Cox & Sons
- St Helens Borough Council
- North West
- Direct award
- 14 March 2025 to 31 August 2025
St Helens Borough Council hired George Cox & Sons, a small business, to build a flood alleviation scheme on West End Road.
The works were part of Sankey Valley Slow the Flow, a natural flood management project. They were designed to manage how water flows and reduce the risk of flooding nearby.
The council ordered the scheme as a call-off through the Rochdale Highways Framework Agreement. The £240,000 contract ran from March 2025 and was due to end in August 2025.
- What
- River restoration and natural flood management
- Supplier
- George Cox & Sons
- Value
- £240,000
- How it was bought
- Direct award
- Dates and next
- Mar 2025 to Aug 2025