Stockton-on-Tees Borough Council hired Liveco Limited after a limited competition to replace the ceilings in two classrooms at Billingham South Community Primary School. The £99,995 job also covered clearing asbestos from the loft spaces and putting the finishes back.
The work followed falls of lath and plaster ceiling in early 2025, when the school was empty, and a structural check that found the ceilings needed stabilising. It was the first phase of a long-term programme to keep the building safe. Work began in July 2026 and was due to end in September 2026.
- What
- Partitions and suspended ceilings
- Supplier
- Liveco Limited
- Value
- £99,995
- How it was bought
- Below threshold - limited competition
- Dates and next
- Jul 2026 to Sep 2026