Taylor and Fraser won the University of Strathclyde's contract for MEP works in the John Anderson (Physics) Building.
The project is funded by a Scottish Funding Council Financial Transactions loan. Taylor and Fraser's part brings new LTHW heating and new ventilation, with air handling units that recover heat. The overcladding and new triple glazed windows are a separate package, with that contractor, D & B Facades UK Ltd, acting as Principal Contractor under CDM. The building stays in use during the works, and the contractor had to bring its own joinery staff.
Two bids came in through an open tender. The award was £2,889,731, a little under the £3,110,000 planning estimate, for a two-year contract with a 12-month defects period.
- What
- Combined M&E building services installation
- Supplier
- Taylor and Fraser
- Value
- £2.89m
- How it was bought
- Open procedure
- 2 bids
- Dates and next