ARK data centre move from two Sussex hospitals goes to Sunspeed
- Sussex Community NHS Foundation Trust
- South East
- Single tender action (below threshold)
- 5 October 2026 to 31 December 2026
Sussex Community NHS Foundation Trust hired Sunspeed Solutions Limited to move its data-centre equipment into ARK Data Centres at Cody Park.
The move covers 36 devices taking up 60U from Brighton General Hospital and Crawley Hospital. The kit moves in phases and is protected in transit.
The trust awarded the £10,115 contract directly in October 2026, without a competition. It is due to finish by the end of December 2026.
Contract ends December 2026
- What
- Household, office and commercial removals
- Supplier
- Sunspeed Solutions Limited
- Value
- £10,115
- How it was bought
- Single tender action (below threshold)
- Dates and next
- Oct 2026 to Dec 2026