J W Bowkett fits LED lighting in five Swansea University buildings
- Swansea University
- Wales
- Open, 5 bids
- 11 September 2025 to 31 March 2026
Swansea University hired J W Bowkett (Electrical Installations) Ltd to replace the lighting and emergency lighting in five of its buildings with LEDs. It was phase 3 of the university's LED Lighting Project. The buildings were Faraday Tower and the Wallace Building on Singleton Campus, the library and School of Management on Bay Campus, and Sketty Lane Sports Centre.
The work also covered changes to the lighting controls and the builders' work that went with them. The buildings stayed in use, so the contractor had to agree a phased decanting plan with the university before starting.
Five firms bid in an open tender, with quality worth 70% of the score and cost 30%. J W Bowkett won in August 2025, and the £1,979,776 contract was due to end in March 2026.
- What
- Lighting replacement and LED upgrades
- Buyer
- Swansea University
- Value
- £1.98m
- How it was bought
- Open
- 5 bids
- Dates and next
- Sep 2025 to Mar 2026