M&E and drainage design for Hedyn's New Hub goes to HWM Building Services
- Tai Hedyn Limited
- Wales
- Below threshold - limited competition
- 1 August 2026 to 14 December 2028
Tai Hedyn Limited has hired HWM Building Services Limited to design the mechanical and electrical services for Hedyn's New Hub, along with the above-ground drainage.
Tai Hedyn chose HWM after a limited competition rather than an open tender. The design contract is worth £98,409 and runs for 29 months, from August 2026 to December 2028.
Contract ends December 2028
- What
- Building services (M&E) engineering design
- Buyer
- Tai Hedyn Limited
- Supplier
- HWM Building Services Limited
- Value
- £98,409
- How it was bought
- Below threshold - limited competition
- Dates and next
- Aug 2026 to Dec 2028