Haywood Crushing clears contamination from Teignbridge's Bradley Mill site
- Teignbridge District Council
- South West
- Direct
- 30 April 2025 to 30 August 2025
Teignbridge District Council paid Haywood Crushing Demolition £308,000 to clear contamination from the Bradley Mill site on Bradley Lane, Newton Abbot.
Haywood was already on site, demolishing the old buildings under an existing contract. Cleaning the ground had been left out of that scope because the Future High Streets Fund money came with tight deadlines. After a funding swap approved by MHCLG freed the Bradley Lane budget from its deadline, the council asked Haywood to price the extra work. Using the firm already on site avoided a second mobilisation and handling the rubble twice.
The job was to remove the main contaminants, the slab and the structures below ground, leaving a levelled hardcore surface and a closure report validating the clean-up. The council awarded it directly, and it was due to run from April to August 2025.
- What
- Contaminated land and groundwater remediation
- Supplier
- Haywood Crushing Demolition Ltd
- Value
- £308,000
- How it was bought
- Direct
- Dates and next
- Apr 2025 to Aug 2025