Healthmatic replaces and refurbishes Teignmouth's public toilets
- Teignmouth Town Council
- South West
- Competitive quotation (below threshold)
- 5 May 2025 to 31 October 2025
Teignmouth Town Council hired Healthmatic to replace or refurbish five of the town centre's public toilets. The work covered new buildings at The Den, Quay Road, Eastcliff and The Point, plus a remodel of the existing block on Lower Brook Street.
The pricing schedules for the new blocks specified charred cedar cladding and metal profiled roofs. The council said it was funding the project alone, and told bidders to price strip foundations, with site conditions to settle the final design.
Healthmatic was chosen after a round of quotes. The £1,083,920 contract started in May 2025 and was due to end in October 2025.
- What
- Toilet and washroom refurbishment
- Supplier
- Healthmatic
- Value
- £1.08m
- How it was bought
- Competitive quotation (below threshold)
- Dates and next
- May 2025 to Oct 2025