Grove West surveys M&E and fire systems at Priorslee Campus
- Telford & Wrekin Council
- West Midlands
- Restricted procedure
- 27 July 2026 to 25 September 2026
Telford & Wrekin Council hired Grove West Property Consultants Ltd to survey the mechanical, electrical and fire systems in buildings at Priorslee Campus.
The survey assessed the existing building systems, checking whether they complied and how well they worked. Grove West was to report on fire safety systems and point out any repairs or maintenance the site needed.
The council awarded the £87,807 contract in July 2026 after a restricted tender. The work was due to end in September 2026.
- What
- Building condition and six-facet surveys
- Value
- £87,807
- How it was bought
- Restricted procedure
- Dates and next
- Jul 2026 to Sep 2026