Vital Energi decarbonises TfL's Allsop Place and Baker Street sites
- Transport for London
- London
- Call-off from a framework agreement
- 14 February 2025 to 3 June 2026
Transport for London hired Vital Energi to cut energy use and emissions at 13-17 Allsop Place and 210-216 Baker Street. The works were part of phase 2 of London's building retrofit (RE:FIT) programme.
Vital Energi's task was to make both sites use less energy, through efficiency measures, energy generation or both. The gains had to be measured and verified. Savings were guaranteed in kWh, and TfL stood to save money through avoided costs or new income.
TfL ordered the work as a call-off worth £4.8m. It started in February 2025 and was due to end in June 2026.
- What
- Public building decarbonisation retrofit
- Buyer
- Transport for London
- Supplier
- Vital Energi
- Value
- £4.84m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2025 to Jun 2026