Alan Dick Communications replaces Windrush Line's BT Megastream circuits
- Transport for London
- London
- Call-off
- 1 July 2026 to 29 June 2027
Transport for London (TfL) hired Alan Dick Communications Limited to replace BT Megastream circuits that have reached the end of their life. The circuits carry GSM-R communications for the London Overground Windrush Line and were due to be decommissioned in 2026.
Alan Dick is swapping them for BT Optical Connect circuits or equivalent, and is responsible for the whole job through to commissioning, to Network Rail standards.
TfL chose the firm through the RISQS dynamic market. The £111,932 contract runs from July 2026 to June 2027.
Contract ends June 2027
- What
- Wide area network (WAN) and site connectivity
- Buyer
- Transport for London
- Supplier
- Alan Dick Communications Limited
- Value
- £111,932
- How it was bought
- Call-off, RISQS
- Dates and next
- Jul 2026 to Jun 2027