Costain Limited (H7-Heathrow) keeps the hardware and software maintenance of Transport for London's CCTV In-Station system.
Costain's earlier contract was about to expire, and TfL needed the legacy system supported until a replacement takes over. TfL relies on the system to meet its duty, under the Traffic Management Act 2004, to keep traffic moving on the road network. The system works with the mission-critical Tunnels CCTV services and is itself classed as Mission Critical, so it cannot be left without support.
TfL awarded the £8.2m contract directly in March 2026. It runs for two years, to March 2028.
Contract ends March 2028
- What
- Rail station and depot CCTV systems
- Buyer
- Transport for London
- Supplier
- Costain Limited (H7-Heathrow)
- Value
- £8.18m
- How it was bought
- Direct
- Dates and next
- Apr 2026 to Mar 2028