Contract awardedWater and sewer network works

Gallows Corner flyover water main diversion, by Northumbrian Water

Transport for London had to move a 36 inch water main out of the way before a new bridge could be built at Gallows Corner.

Northumbrian Water carried out the diversion, combining tunnelling with open cut construction to relocate the existing main.

TfL awarded the work directly, at £16,235,980, and the contract was due to end in March 2026.

What
Water and sewer network works
Value
£16.2m
How it was bought
Direct
Dates and next
Nov 2025 to Mar 2026

How it was bought

1 official notice
  1. 7 Nov 2025Award noticeFind a Tender
  2. 19 Nov 2025Contract starts
  3. 6 Mar 2026Contract ends

How it compares

With every water and sewer network works award since 2021

Half of awards fall between £53,322 and £822,198Median £142,682

Awards
147
Firms that won them
122
Median award
£142,682
of 129 with a value
This award
Bigger than 92%
of them
Typical length
6 months
In London
15 awards

Northumbrian Water ranks 2nd of 122 firms for water and sewer network works awards since 2021.

RankFirmAwardsValue
1Locked8£7.58m
2Northumbrian Water Won this one7£17.4m
2Locked7£15.9m
4Locked5£2.85m
4Locked5£792,141
6Locked4£4.61m
See who wins this work

Figures to 21 November 2026

Water and sewer network works at other buyers

Transport for London has awarded 1,169 contracts since 2021.

See Transport for London's page
  • Northumbrian Water has won 31 public contracts since 2021.

1 water and sewer network works tender is open now

See it
More water and sewer network works contracts awarded in 2025