HV feeder cable renewal: Transport for London needs cable operatives
- Transport for London
- London
- Call-off
- 26 April 2027 to 25 April 2028
Transport for London plans to hire experienced operatives to help renew high voltage (HV) feeder cables across its network. It expects to need about 800 shifts over 12 months to install the first cable section.
The work is heavy cable installation in rail and tunnel settings. Crews would handle HV cables of about 20 kg per metre, run London Underground cable trains and move drums of up to 5 tonnes.
TfL plans to buy through RISQS, which Rail Safety & Standards Board Ltd (RSSB) runs as a dynamic market for cable procurement. The work is estimated at £450,000 for a 12-month contract from April 2027.
Due in 78 days· 8 Feb 2027
- What
- Construction and maintenance trades labour
- Buyer
- Transport for London
- Estimated value
- £450,000
- How it will be bought
- Call-off, RISQS
- Responses due
- 8 Feb 2027
- Contract dates
- Apr 2027 to Apr 2028