London Underground lift maintenance for TfL goes to Schindler
- Transport for London
- London
- 3 bids
Transport for London chose Schindler to maintain about 112 London Underground lifts, mainly on the Jubilee, Northern and Piccadilly lines. London Underground maintains around 100 of its lifts in-house through its Direct Labour Organisation.
The work runs from planned upkeep to round-the-clock call-outs when lifts break down or trap passengers.
Three bids came in. The award, made in March 2026, was £53,598,288, below the estimate. The contract runs for five years, and extensions of up to four more could take it to April 2035.
- What
- Passenger and goods lifts
- Buyer
- Transport for London
- Supplier
- Schindler
- Value
- £53.6m
- How it was bought
- Not published
- 3 bids
- Dates and next
- 31 Mar 2026