Kier upgrades Thames Water's Maple Lodge sewage works for £280m
- Thames Water
- South East
- Selective
- 1 April 2026 to 29 March 2030
Kier is upgrading Thames Water's Maple Lodge sewage treatment works.
The work includes a new activated sludge plant, Bank C, and eight final settlement tanks 28m across. Two tertiary solids removal plants will treat the effluent, one for the new bank and one for Banks A and B. Chemical dosing at the primary and secondary stages helps remove phosphorus. Storm flows get their own tank, outfall to the river and return pumping station, and three storm tanks become primary settlement tanks. Redundant structures are demolished, and the power supply, SCADA and standby generation are upgraded.
Kier was chosen in February 2026, with technical and commercial scores each worth 40% and behaviours 20%. The award was £280m, the top of a range Thames Water put at about £140m to £280m. The four-year contract runs to March 2030.
Contract ends March 2030
- What
- Water and wastewater treatment works and utility MEICA
- Buyer
- Thames Water
- Supplier
- Kier
- Value
- £280m
- How it was bought
- Selective
- Dates and next
- Apr 2026 to Mar 2030