Futures Afloat buoy handling ships for Trinity House go to Vard Group
- Trinity House
- London
- Competitive flexible procedure, 2 bids
- 22 July 2026 to 29 October 2032
Vard Group AS will design and build two identical buoy handling ships for Trinity House under the Futures Afloat programme. They replace THV Patricia and THV Galatea, the ageing multi-functional buoy tenders. Trinity House is the General Lighthouse Authority for England, Wales, the Channel Islands and Gibraltar.
Each ship has its own contract. The first is due for delivery on 3 April 2029 and is worth £100.9m. The second follows on 29 October 2029, at £92.4m.
Two bids came in, judged 82% on quality and 18% on price. Vard Group won in May 2026, for £193.3m in all. Its warranty and defect duties run to October 2032.
Contract ends October 2032
- What
- Vessel supply and shipbuilding
- Buyer
- Trinity House
- Supplier
- Vard Group AS
- Value
- £193.3m
- How it was bought
- Competitive flexible procedure
- 2 bids
- Dates and next
- Jul 2026 to Oct 2032