Tees Valley Combined Authority (TVCA) hired FarrPoint for a feasibility study on whether to invest in an IoT network for the area.
The study made up phase 1, capped at £62,440. If it backed the investment, TVCA could have asked FarrPoint to stay on for design, procurement and deployment support, but those later phases were not guaranteed. TVCA's early market engagement spoke of a LoRaWAN network.
Five bids came in, with quality worth 75% of the score and price 25%. FarrPoint, a small business, won in April 2026. The £150,000 award was the most the contract could reach with every phase delivered, and the contract ended in September 2026.
- What
- Network and connectivity consultancy
- Supplier
- FarrPoint
- Value
- £150,000
- How it was bought
- Open
- 5 bids
- Dates and next
- May 2026 to Sep 2026
- Option to Dec 2027