Contract awardedCall-offFootways, cycleways and path construction

Middlesbrough to Redcar Active Travel Corridor brings in Balfour Beatty

Tees Valley Combined Authority (TVCA) has brought in Balfour Beatty early to help develop the Middlesbrough to Redcar Active Travel Corridor.

The scheme sits within the City Region Sustainable Transport Settlement (CRSTS) programme. Under an NEC4 Professional Service Short Contract, Balfour Beatty advises on cost, risk and buildability, and helps refine the detailed design and the programme. TVCA intends to hand the same firm the construction under an NEC4 Engineering and Construction Contract, once a target cost and approvals are in place.

TVCA ordered the early phase through the SCAPE Civil Engineering Framework - EWNI and awarded it in October 2026. The £288,000 award covers only this phase, which runs to February 2027. The construction value will not be known until the early work is done.

Alert me to similar tenders

Contract ends February 2027

What
Footways, cycleways and path construction
Value
£288,000
How it was bought
Call-off, SCAPE Civil Engineering Framework - EWNI
Dates and next
Oct 2026 to Feb 2027

How it was bought

1 official notice
  1. 30 Sep 2026Bids closed
  2. 6 Oct 2026Contract starts
  3. 26 Oct 2026Award noticeDelta eSourcing
  4. 19 Feb 2027Contract ends

Tees Valley Combined Authority has bought this 3 times since 2021

Last bought
Oct 2026
Typical length
5 months
Typical value
£500,000
Suppliers used
2
AwardedContractWon byValue
Oct 2026This purchase4 monthsBalfour Beatty£288,000
Sep 2026Locked5 monthsLocked£500,000
Sep 2026Locked5 monthsLocked£500,000

Suppliers Tees Valley Combined Authority has used

SupplierContractsValue
Locked2£1m
Balfour Beatty Won this one1£288,000
See the contracts and who won them

Figures to 21 November 2026

How it compares

With every footways, cycleways and path construction award since 2021

Half of awards fall between £45,776 and £355,821Median £112,218

Awards
600
Firms that won them
247
Median award
£112,218
of 572 with a value
This award
Bigger than 72%
of them
Typical length
3 months
In North East
24 awards

Balfour Beatty ranks 15th of 247 firms for footways, cycleways and path construction awards since 2021.

RankFirmAwardsValue
1Locked51£3.93m
2Locked28£5.93m
2Locked28£1.65m
4Locked23£1.56m
5Locked15£1.37m
6Locked12£24.6m
15Balfour Beatty Won this one5£32.5m
See who wins this work

Footways, cycleways and path construction at other buyers

Tees Valley Combined Authority has awarded 562 contracts since 2021.

See Tees Valley Combined Authority's page

5 footways, cycleways and path construction tenders are open now

See them
More footways, cycleways and path construction contracts awarded in 2026