Oxford Mechanical & Electrical installs plant at UKAEA's Building D15
- UK Atomic Energy Authority
- South East
- Below threshold - open competition
- 2 September 2026 to 28 February 2027
The UK Atomic Energy Authority hired The Oxford Mechanical & Electrical Company Ltd to install electrical plant and equipment.
The work covers kit within and linked to the Building D15 High Voltage Power Supplies. UKAEA wanted a contractor able to provide staff experienced in electrical installation at industrial sites or large scientific facilities. Bids were scored 75% on price and 25% on technical quality.
The £190,000 contract started in September 2026. An extension of three or six months could take it to August 2027.
Contract ends February 2027
- What
- Electrical installation, rewiring and repairs
- Value
- £190,000
- How it was bought
- Below threshold - open competition
- Dates and next
- Sep 2026 to Feb 2027
- Option to Aug 2027