Boxxe supplies UKAEA's replacement FREIA cluster at Culham Campus
- UK Atomic Energy Authority
- South East
- Direct award
- 1 October 2026 to 1 October 2031
UK Atomic Energy Authority is replacing the existing FREIA high-performance computing cluster at Culham Campus with a new cluster supplied by Boxxe. The contract also covers support services for the replacement system.
The authority awarded the £995,531 contract directly in September 2026. It runs for five years, through to October 2031.
Contract ends October 2031
- What
- High-performance computing (HPC)
- Supplier
- Boxxe
- Value
- £995,531
- How it was bought
- Direct award
- Dates and next
- Oct 2026 to Oct 2031