Safety case peer review for UKAEA's fusion facilities goes to Arcadis
- UK Atomic Energy Authority
- South East
- Open procedure, 20 bids
- 1 June 2026 to 31 May 2029
The UK Atomic Energy Authority, based at Culham in Oxfordshire, hired Arcadis to give engineering support, as needed, to its safety case work for fusion research facilities.
Its Safety Case Engineering Group prepares those cases for UKAEA's own facilities and for others in the wider fusion community. The cases show that process hazards, radiological and otherwise, are found and controlled as the law requires.
Twenty bids came in after an open tender, with quality counting for 70% of the score and price 30%. Arcadis won in May 2026 at £500,000. The three-year contract can be extended to May 2030.
Contract ends May 2029
- What
- Nuclear technical support, engineering and safety
- Supplier
- Arcadis
- Value
- £500,000
- How it was bought
- Open procedure
- 20 bids
- Dates and next
- Jun 2026 to May 2029
- Option to May 2030