STRIDE IT hosting for UKAEA comes from Dell Technologies
- UK Atomic Energy Authority
- Other -
- 1 April 2026 to 31 May 2029
The UK Atomic Energy Authority (UKAEA) is paying Dell Technologies to host its IT equipment off-site for STRIDE Phase 1.
Dell's colocation service covers rented space and security for the hardware, plus installation work as far as the cabinet.
UKAEA ordered the service through HealthTrust Europe's Enterprise Solutions framework in February 2026. The £8.4m contract, excluding VAT, runs to May 2029.
Contract ends May 2029
- What
- Data centre colocation
- Supplier
- Dell Technologies
- Value
- £8.4m
- How it was bought
- Other -
- Dates and next
- Apr 2026 to May 2029