1894 Building switch room design for UKRI goes to CB3 Design Associates
- UK Research and Innovation (UKRI)
- Scotland
- Below threshold - limited competition
- 1 October 2026 to 31 March 2027
UK Research and Innovation (UKRI) has hired CB3 Design Associates Ltd to design phase 1 of a central plant building at the Royal Observatory, Edinburgh.
Phase 1 is an open-to-air enclosure for packaged plant units, based on LDN Architects' 2024 proposals. CB3 also does early design work on Phase 2, so the layout of the whole building is settled during Phase 1. Work to the existing buildings is not included.
UKRI awarded the £34,000 contract after a limited competition in October 2026. It runs to March 2027.
Contract ends March 2027
- What
- Architectural design services
- Supplier
- CB3 Design Associates Ltd
- Value
- £34,000
- How it was bought
- Below threshold - limited competition
- Dates and next
- Oct 2026 to Mar 2027