TS2 Methane Moderator for UKRI comes from Fieldhouse Engineering
- UK Research and Innovation (UKRI)
- South West
- Direct
- 16 July 2025 to 31 October 2025
UK Research and Innovation (UKRI) awarded Fieldhouse Engineering a contract to finish and deliver the TS2 Methane Moderator.
Fieldhouse was to finish and test the Internal Head Assembly as well as delivering the moderator. UKRI said only one supplier could do the work, for technical reasons, so the contract was awarded directly with no competition.
The £24,300 contract ran from July 2025 and was due to end in October 2025.
- What
- Bespoke research rigs and experimental equipment
- Supplier
- Fieldhouse Engineering Ltd
- Value
- £24,300
- How it was bought
- Direct
- Dates and next
- Jul 2025 to Oct 2025