East Kirkby Engineering replaces gas pipework at Lincoln County Hospital
- United Lincolnshire Teaching Hospitals NHS Trust
- East Midlands
- Call-off from a framework agreement
- 10 February 2025 to 31 March 2025
United Lincolnshire Teaching Hospitals NHS Trust hired East Kirkby Engineering Co Limited to replace the CPU gas pipework at Lincoln County Hospital. The new pipework was meant to keep gas distribution at the hospital in line with safety standards.
The trust ordered the works as a call-off from a framework agreement. The £47,954 contract started in February 2025 and was due to end in March 2025.
- What
- Commercial gas pipework and gas safety testing
- Value
- £47,954
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2025 to Mar 2025