Balfour Beatty removes RAAC from JCMB Level 2 and the Joseph Black Labs
- University of Edinburgh
- Scotland
- Open procedure, 1 bid
The University of Edinburgh appointed Balfour Beatty to remove RAAC panels at JCMB Level 2 and the Joseph Black Labs. As principal contractor, Balfour Beatty takes charge of the site and the structural repairs needed to take out and replace the reinforced autoclaved aerated concrete. The work takes place on a working university campus.
Balfour Beatty's was the only bid, and the contract is worth £5.9m.
- What
- RAAC and structural remediation of buildings
- Supplier
- Balfour Beatty
- Value
- £5.92m
- How it was bought
- Open procedure
- 1 bid
- Dates and next
- 15 Nov 2024