Balfour Beatty plans Arts and Sports Bridges work at University of Lincoln
- University of Lincoln
- East Midlands
- Call-off
- 21 September 2026 to 28 May 2027
The University of Lincoln needed a contractor to plan potential works on its Arts and Sports Bridges, which both span a live railway line.
Because the railway below stays in use, the university wanted an experienced specialist to plan the order and timing of any works.
The university ordered the work through the single-contractor SCAPE Civil Engineering Framework - EWNI, appointing Balfour Beatty directly. The £197,000 pre-construction services run for eight months, from September 2026 to May 2027.
Contract ends May 2027
- What
- Bridges and highway structures
- Supplier
- Balfour Beatty
- Value
- £197,000
- How it was bought
- Call-off, SCAPE Civil Engineering Framework - EWNI
- Dates and next
- Sep 2026 to May 2027