Contract awardedHV and LV distribution, switchgear and substations
Arts substation cabling at the University of Sussex goes to Aureos
- University of Sussex
- South East
- 13 March 2026 to 31 March 2027
The University of Sussex hired Aureos to lay cabling between the Arts substation and the main intake panel. The cable reinstates the ring main linking the two.
The cabling is one part of the wider development works on the university's west slope.
The contract is worth £221,319 and runs from March 2026 to March 2027.
Alert me to similar tenders
Contract ends March 2027
- What
- HV and LV distribution, switchgear and substations
- Buyer
- University of Sussex
- Supplier
- Aureos
- Value
- £221,319
- How it was bought
- Not published
- Dates and next
- Mar 2026 to Mar 2027