Nuneaton Library and Business Centre goes to GMI Construction Group
- Warwickshire County Council
- West Midlands
- Competitive flexible procedure, 4 bids
- 21 August 2026 to 31 December 2027
Warwickshire County Council chose GMI Construction Group Plc to design and build a new library and business centre in Nuneaton. The job also covers enabling works across the whole site. The design had reached RIBA Stage 3 before the tender, and the contractor takes on all design work from there.
Mace Consult, the council's lead consultant, stays on to run the project and keep control of costs and the contract through RIBA Stages 5 to 7.
Four bids came in. Experience carried 40% of the score, risk management 20%, NEC experience and statutory roles 15% each, and social value 10%. GMI Construction Group, a small business, won the £17.3m contract, which runs from August 2026 to December 2027.
Contract ends December 2027
- What
- New-build construction of non-residential buildings
- Supplier
- GMI Construction Group Plc
- Value
- £17.3m
- How it was bought
- Competitive flexible procedure
- 4 bids
- Dates and next
- Aug 2026 to Dec 2027