Interclass designs and builds Upper Lighthorne Primary School
- Warwickshire County Council
- West Midlands
- Open procedure, 5 bids
- 12 August 2026 to 24 February 2028
Warwickshire County Council hired Interclass to design and build Upper Lighthorne Primary School under a two-stage contract.
The school is planned for two-form entry, with enabling works so it can later grow to three-form entry. The design had reached RIBA Stage 3, drawn up first by Pick Everard and then Gleeds. The contractor now does all the design work, while Gleeds stays on to manage costs, administer the contract and run the project.
Five bids came in to an open tender scored 50% on cost, 40% on quality and 10% on social value. The award was £16.5m against an estimate of £13.3m. The contract is set to end in February 2028, but runs until the school is finished.
Contract ends February 2028
- What
- New-build construction of non-residential buildings
- Supplier
- Interclass
- Value
- £16.5m
- How it was bought
- Open procedure
- 5 bids
- Dates and next
- Aug 2026 to Feb 2028
- Option to Feb 2029