McCarthy Contractors builds new revetment on the River Tawe at SA1
- Llywodraeth Cymru / Welsh Government
- Wales
- Open, 3 bids
- 2 November 2026 to 2 March 2027
Llywodraeth Cymru / Welsh Government has hired McCarthy Contractors (Bridgend) Ltd to build new revetment along the River Tawe at SA1, Swansea. The scheme had reached detailed design, and a FRAP licence and planning permission were already in place.
The contractor will also lay drainage, manage traffic, keep the public and stakeholders informed and look after the works through the defects period. Shoreline Management Wales (SMW) acts as project manager, supervisor and principal designer for the Welsh Government.
Three firms bid in an open tender. The Welsh Government awarded the £230,657 contract in October 2026, and it is due to end in March 2027. The contract can be extended by up to a month.
Contract ends March 2027
- What
- Flood defence and flood alleviation works
- Value
- £230,657
- How it was bought
- Open
- 3 bids
- Dates and next
- Nov 2026 to Mar 2027
- Option to Apr 2027