Enable Infrastructure takes on Halewick Lane battery storage site Phase 3
- West Sussex County Council
- South West
- Open procedure (above threshold)
- 10 October 2025 to 9 October 2028
West Sussex County Council has appointed Enable Infrastructure Ltd as contractor for Phase 3 of the Halewick Lane Battery Energy Storage Site. The award is a pre-construction services agreement (PCSA), which comes before the main works to build the site.
Under the PCSA, the contractor takes on the design and planning of the battery storage facility ahead of construction.
The council ran an open tender. The contract is worth £15.1m and runs from October 2025 to October 2028.
Contract ends October 2028
- What
- Solar PV and battery storage
- Supplier
- Enable Infrastructure Ltd
- Value
- £15.1m
- How it was bought
- Open procedure (above threshold)
- Dates and next
- Oct 2025 to Oct 2028