Westmorland and Furness Council is paying Story Contracting to design and rebuild Broadhead Bridge, in a two-stage contract. Building is planned for the in-river working window in 2027, if not earlier.
The work starts with ground investigation, a scour assessment and approvals such as the LLFA's. Story Contracting also has to agree a Basic Asset Protection Agreement with Network Rail and work with the council's legal team and landowners. On site, the contractor clears the rock rolls, repairs the culvert, builds and repairs training walls and reinstates the road approach.
The council awarded the contract in July 2026 at £194,563, and it runs to May 2027.
Contract ends May 2027
- What
- Bridges and highway structures
- Supplier
- Story Contracting
- Value
- £194,563
- How it was bought
- Other -
- Dates and next
- Jul 2026 to May 2027
- Being re-tendered now