Metcalfe Plant Hire to saddle and repair Town End (Orton) Bridge
- Westmorland and Furness Council
- North West
- Call-off from a framework agreement
- 2 November 2026 to 30 September 2027
Westmorland and Furness Council hired Metcalfe Plant Hire to design and build repairs to Town End (Orton) Bridge.
Besides repairs to the arch barrels and the western flood span, the contractor will saddle the bridge's two main spans. The council ordered the work as a call-off from a framework agreement.
The £106,583 contract was awarded in September 2026 and runs to September 2027.
Contract ends September 2027
- What
- Bridges and highway structures
- Supplier
- Metcalfe Plant Hire
- Value
- £106,583
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Nov 2026 to Sep 2027