Smoke and fire damper servicing for WHSCT goes to Safegard Systems
- Western Health and Social Care Trust
- Northern Ireland
- Direct
- 1 February 2026 to 31 August 2030
Western Health and Social Care Trust pays Safegard Systems to look after the Safegard smoke and fire dampers in its buildings. The work is routine servicing and maintenance to keep the dampers meeting fire safety standards.
The trust awarded the £484,959 contract directly. It runs to August 2030, and yearly extensions could take it to August 2033.
The plan is to fold the work into the Northern Ireland Health & Social Care contract for Maintenance of Ventilation Systems (including Smoke Dampers) when that is renewed. The extensions would give time to finish that regional re-tender, or cover the case where it ends without an award.
Contract ends August 2030
- What
- Fire and smoke damper testing
- Supplier
- Safegard Systems
- Value
- £484,959
- How it was bought
- Direct
- Dates and next
- Feb 2026 to Aug 2030
- Option to Aug 2033