WJ Structures steam cleans the Leigh Turnpike/Library building for Wigan
- Wigan Council
- North West
- Below threshold - without competition
- 7 September 2026 to 30 September 2026
Wigan Council hired WJ Structures Ltd to clean all four sides of the Leigh Turnpike/Library building.
The council needed it done quickly, ahead of the official opening of Leigh Civic Square. The work called for the DOFF Integra system, which cleans with superheated water at low pressure. The cleaning was to lift algae, grime and pollution staining from the bare concrete without damaging the surface.
The £33,615 contract was awarded directly, without a competition, and was due to end in September 2026.
- What
- External building, facade and roof cleaning
- Buyer
- Wigan Council
- Supplier
- WJ Structures Ltd
- Value
- £33,615
- How it was bought
- Below threshold - without competition
- Dates and next
- Sep 2026 to Sep 2026