Electrification Construction Services handles switching on Metro Line One
- West Midlands Combined Authority
- West Midlands
- Direct
- 3 June 2025 to 3 August 2025
West Midlands Combined Authority hired Electrification Construction Services Limited to carry out isolation switching on Midland Metro Line One. The switching was needed so that high priority inspections of the overhead line equipment could be completed.
The firm was the only supplier then trained for isolation switching on Line One, and the authority awarded it the work directly. The £28,985 contract covered two months and was due to end in August 2025.
- What
- Rail electrification and signalling
- Value
- £28,985
- How it was bought
- Direct
- Dates and next
- Jun 2025 to Aug 2025