Pell Frischmann validates SCOOT signals in West Bromwich for WMCA
- West Midlands Combined Authority
- West Midlands
- Call-off from a framework agreement
- 2 March 2026 to 31 August 2026
West Midlands Combined Authority hired Pell Frischmann for two separate pieces of traffic signal work in West Bromwich.
The authority wanted extra remedial works on the Sprint 1 project. It also wanted the town's SCOOT (Split Cycle Offset Optimisation Technique) signal systems validated, so that signals and the wider network performed well.
The authority ordered the work from a framework. The £43,620 contract started in March 2026 and was due to end in August 2026.
- What
- Traffic signals and intelligent transport systems
- Supplier
- Pell Frischmann
- Value
- £43,620
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Mar 2026 to Aug 2026