Lightning protection checks for Woking go to Spotlight Construction
- Woking Borough Council
- South East
- Below threshold - limited competition
- 1 April 2026 to 31 March 2028
Woking Borough Council has hired Spotlight Construction to keep its lightning protection systems in working order. The firm tests, inspects and maintains the systems and runs the contract day to day. It can also quote for one-off repairs when they are needed.
The council awarded the £40,000 contract after a limited competition. It covers two years from April 2026, and two optional one-year extensions could take it to March 2030.
Contract ends March 2028
- What
- Lightning protection and earthing
- Supplier
- Spotlight Construction
- Value
- £40,000
- How it was bought
- Below threshold - limited competition
- Dates and next
- Apr 2026 to Mar 2028
- Option to Mar 2030