AECOM updates the A454 Phase 3 business case for Wolverhampton
- Wolverhampton City Council
- Call-off
- 6 October 2026 to 30 July 2027
Wolverhampton City Council hired AECOM to bring the data, modelling and design for the A454 Phase 3 scheme up to date. The council is running the work on behalf of Black Country Transport (BCT).
The scheme covers the A454 where it meets Neachells Lane and Noose Lane. AECOM's updates are meant to move the scheme towards a finished outline business case.
The council awarded the £168,312 contract directly in October 2026, ordering through ESPO's 664_25 Consultancy Services framework (Lot 5). It is due to end in July 2027.
Contract ends July 2027
- What
- Transport modelling and scheme appraisal
- Supplier
- AECOM
- Value
- £168,312
- How it was bought
- Call-off, ESPO
- Dates and next
- Oct 2026 to Jul 2027