Ridge Environmental writes WRAP's landfill bans HRA for Northern Ireland
- Waste and Resources Action Programme (WRAP)
- South East
- Below threshold - award under framework
- 9 June 2026 to 31 July 2026
Waste and Resources Action Programme (WRAP) ordered a Habitats Regulatory Assessment for Northern Ireland from Ridge Environmental Limited, a small business.
The assessment looked at landfill bans and their possible effect on protected habitats. WRAP placed the order directly under lot 4 of its FRA082 framework.
The £12,000 contract was awarded in June 2026. It could run to September 2026 if the deliverables needed more time.
- What
- Habitats Regulations Assessment
- Supplier
- Ridge Environmental Limited
- Value
- £12,000
- How it was bought
- Below threshold - award under framework
- Dates and next
- Jun 2026 to Jul 2026
- Option to Sep 2026