Supply and Install of electrical clean steam generator (NIBF1)
- Centre for Process Innovation
- North East
- Direct award
- 26 March 2026 to 25 March 2029
Purchase and installation of an electrical clean steam generator for a biotechnology pilot plant. The unit must be constructed from 316 stainless steel, operate on a maximum 200amp supply, and deliver over 175 kg/hr of steam at 3 barg. It is designed for indoor plant room installation to support bioreactor sterilisation and heating, requiring compatibility with reverse osmosis demineralised water feeds.
- Awarded value
- £55k
- As published
- Published
- 26 March 2026
- Contract length
- 36 months
- Ends 25 March 2029