Allerton OHLE Isolations
- Northern Trains Limited
- Yorkshire and the Humber
- Invited to quote
- 26 March 2026 to 2 September 2026
Design and construction of motor-operated OHLE isolators on three roads within a train maintenance shed. Work includes removing manual operating gear, installing motor units with new support steelwork, fitting limit switch assemblies, and performing functional testing. The contractor acts as principal designer and contractor, coordinating with the Depot Protection System specialist and Network Rail for engineering assurance and isolation diagram updates.
- Awarded value
- £241k
- As published
- Published
- 31 March 2026
- Contract length
- 5 months
- Ends 2 September 2026