Contract awardedShipbuilding

Shipyard Detailed Design and Build Contract Vehicle and Passenger Carrying Ferries

Detailed design and construction of seven replacement vehicle and passenger ferries. The scope includes developing technical drawings and calculations, vessel construction, sea trials, and commissioning in compliance with classification society and UK flag state authority requirements. The project involves ongoing oversight by an on-site client project team throughout the build process.

Awarded value
£148m
As published
Published
16 July 2024
Awarded
28 March 2025
Remontowa Shipbuilding S.A.
Contract length
47 months
Ends 7 March 2029

What the contract covers

Single contract / independent lot

Shipbuilding and marine engineering services for the detailed design, construction, testing, and delivery of commercial vehicle and passenger carrying vessels.

  • Detailed design and build of seven replacement vessels
  • Detailed designs, calculations and drawings of the vessels for approval
  • Design, construction, testing and survey, launch, equipping, sea trials and completion of the vessels in accordance with the approved detailed designs, calculations and drawings

Terms and requirements

Contract type
Single contract / independent lot
Procedure
Selective procedure
Initial term
47 months
Contract dates
28 March 2025 to 7 March 2029
Certifications asked for
None stated
Lots
1
Suitable for SMEs
Not stated
Category
Goods
CPV codes
34500000, 34510000, 34512000, 34512100

Services in this contract

Lifecycle

  1. Published
  2. Contract awardedto Remontowa Shipbuilding S.A.
  3. Contract starts
  4. Contract ends
The buyer

Caledonian Maritime Assets Ltd

Type
Locked
Contracts, 24 months
Locked
Recorded value
Locked
Typical contract
Locked
Shipbuilding contracts, 24 months
Locked
Buys mostLocked
Contact details
Email
Locked
Phone
Locked
Website
Locked
Address
Locked
See everything Caledonian Maritime Assets Ltd buys
The supplier

Remontowa Shipbuilding S.A.

Contracts won, 24 months
Locked
Value won, 24 months
Locked
Buyers, 24 months
Locked
Size
Locked
Main buyersLocked
Contact details
Phone
Locked
Website
Locked
See everything Remontowa Shipbuilding S.A. has won

Similar shipbuilding contracts and prices

13 shipbuilding contracts were awarded in Scotland in the last 24 months. See who won them and what they went for, next to this one.

See who won them →

Cite this contract

Link
https://bidskim.com/tender/359221/shipyard-detailed-design-and-build-contract-vehicle-and-passenger-carrying-ferri
Buyer reference
org-187
Open contracting ID
ocds-r6ebe6-0000771893
Last checked
5 November 2026

Caledonian Maritime Assets Ltd. Shipyard Detailed Design and Build Contract Vehicle and Passenger Carrying Ferries. Contract award, 16 July 2024. BidSkim, https://bidskim.com/tender/359221/shipyard-detailed-design-and-build-contract-vehicle-and-passenger-carrying-ferri (accessed 5 November 2026).