Autonomous Waste Sorting and Segregation (Auto-SAS)
- Nuclear Decommissioning Authority
- 1 April 2025 to 31 March 2029
This innovation partnership involves a two-phase project to design, build, and test an integrated robotic platform off-site, followed by on-site installation, commissioning, and operational testing at a nuclear licensed facility. The system must comply with rigorous safety and design justification processes, including Factory Acceptance Testing and Site Acceptance Testing, to demonstrate autonomous waste handling capabilities.
- Awarded value
- £5m
- As published
- Published
- 1 July 2024
- Find a Tender
- Contract length
- 48 months
- Ends 31 March 2029